News

Court rulings gives big boost to high-speed rail

Judge rejects lawsuit from Central Valley that sought to stop controversial project

California's high-speed rail system surged past a major legal obstacle this week when a Sacramento Superior Court judge tossed out a long-simmering lawsuit from the Central Valley.

The 2011 suit by John Tos, Aaron Fukuda and the County of Kings, maintained that the proposed rail system violates the provisions of Proposition 1A, a 2008 bond measure that allocated $9.95 billion for the San Francisco-to-Los Angeles rail system.

By revising the design of the system so that high-speed rail will now share a set of tracks with Caltrain along the Peninsula, the agency has strayed from the plans that were presented to the voters before the 2008 vote, attorneys for the plaintiffs argued during a three-day hearing in Sacramento in February. The initial plan called for a four-track alignment between San Francisco and San Jose.

The change, the plaintiffs have argued, is significant because the blended system would undermine the rail system's ability to achieve the state-mandated goal of going from San Francisco to Los Angeles in two hours and 40 minutes. This would make the rail system ineligible for the bond funds and for federal funds, which are contingent on having state money being available.

In a judgement issued March 4, Judge Michael P. Kenny concurred that the California High Speed Rail Authority does not have sufficient evidence at this time to show that it can comply with all of the requirements of the 2008 bond. The authority, which is charged with building the $64 billion project, has not yet provided the analysis of the trip time from San Jose to the San Francisco Transbay Terminal (its analysis still relies on San Francisco's lone Caltrain station at 4th and King streets, which is about 1.3 miles south of Transbay Terminal), Kenny noted. Nor has it shown that it can achieve a five-minute headway (the amount of time between trains), as mandated by law.

Help sustain the local news you depend on.

Your contribution matters. Become a member today.

Join

However, Kenny wrote, the rail authority "may be able to accomplish these objectives at some point in the future." He called high-speed rail an "ongoing, dynamic, changing project" and concurred with a recent ruling from the state Court of Appeal, which found that because the project is in flux, it cannot determine whether the project would meet the requirements of the Bond Act.

"There is no evidence currently before the Court that the blended system will not comply with the Bond Act system requirements," Kenny wrote in his ruling. "Although Plaintiffs have raised compelling questions about potential future compliance, the Authority has not yet submitted a funding plan seeking to expend Bond Act funds. Thus, the issue of the project's compliance with the Bond Act is not ripe for review."

Without the necessary analysis, Kenny reasoned, it is premature to determine whether the proposed system would meet the requirements of the 2008 bond. There are, as of today, "still too many unknown variables, and in absence of a funding plan, too many assumption that must be made as to what the Authority's final decisions will be."

By denying the plaintiff's request that the project be halted, Kenny handed a massive victory to what has been a deeply divisive and controversial project. While supporters, including Gov. Jerry Brown and the Democratic majority in the Legislature, consistently laud high-speed rail as a much needed solution to ease traffic congestion, create jobs and reduce greenhouse-gas emissions, critics have panned it as a "boondoggle" that has nowhere near the funds it needs to become a reality.

Palo Alto officials had initially supported the project but ultimately turned against it, passing in 2011 a unanimous resolution calling for the project's termination. At the time, residents and council members raised doubts about the system's financial projections, ridership estimates and proposed alignment, which initially called for four tracks, with an elevated berm in the middle for the new bullet train.

Stay informed

Get the latest local news and information sent straight to your inbox.

Stay informed

Get the latest local news and information sent straight to your inbox.

By shifting to the blended approach, which was first proposed by Peninsula lawmakers in 2012, the rail authority has helped qualm some of these anxieties. The project also picked up some momentum last month, when the rail authority released a new business plan showing the price tag dipping from $67.6 billion two years ago to $64.2 billion.

The new business plan also announced a major change of direction for the rail authority: Rather than launching construction of the line exclusively in Central Valley, the agency now plans to build the first operating segment between San Francisco and Bakersfield.

In presenting the business plan to the rail authority's board of director's Tuesday morning, rail authority CEO Jeff Morales called the new proposal "the game-changer, in terms of delivering the program."

The business plan relies mostly on bond funds and on proceeds from the state's cap-and-trade program for building the first operating segment, between the Bay Area and Central Valley. Rail officials hope further improvements and expansions would be financed, at least in part, by private investments and federal contributions.

"For the first time, within available resources, we can actually project out to delivering an operating system," Morales told the board Tuesday.

Most Viewed Stories

Most Viewed Stories

The board voiced no major concerns Tuesday about the dramatic change of direction in the new business plan. Board member Daniel Curtin said he is "very excited about the new development," which he said would bring new economic opportunities to the two regions that would be connected by high-speed rail.

"We all see the economic pressures being put on the Bay Area by Silicon Valley," Curtin said. "This is a whole change in how that can be approached that, really to me, is the first signal of what high-speed rail will do for California."

Board Chair Dan Richard agreed and lauded the plan for laying out for the public "how we can build the system."

"What is really here, is the sense that we can build this now," Richard said.

Craving a new voice in Peninsula dining?

Sign up for the Peninsula Foodist newsletter.

Sign up now
Gennady Sheyner
 
Gennady Sheyner covers the City Hall beat in Palo Alto as well as regional politics, with a special focus on housing and transportation. Before joining the Palo Alto Weekly/PaloAltoOnline.com in 2008, he covered breaking news and local politics for the Waterbury Republican-American, a daily newspaper in Connecticut. Read more >>

Follow on Twitter @mvvoice, Facebook and on Instagram @mvvoice for breaking news, local events, photos, videos and more.

Court rulings gives big boost to high-speed rail

Judge rejects lawsuit from Central Valley that sought to stop controversial project

California's high-speed rail system surged past a major legal obstacle this week when a Sacramento Superior Court judge tossed out a long-simmering lawsuit from the Central Valley.

The 2011 suit by John Tos, Aaron Fukuda and the County of Kings, maintained that the proposed rail system violates the provisions of Proposition 1A, a 2008 bond measure that allocated $9.95 billion for the San Francisco-to-Los Angeles rail system.

By revising the design of the system so that high-speed rail will now share a set of tracks with Caltrain along the Peninsula, the agency has strayed from the plans that were presented to the voters before the 2008 vote, attorneys for the plaintiffs argued during a three-day hearing in Sacramento in February. The initial plan called for a four-track alignment between San Francisco and San Jose.

The change, the plaintiffs have argued, is significant because the blended system would undermine the rail system's ability to achieve the state-mandated goal of going from San Francisco to Los Angeles in two hours and 40 minutes. This would make the rail system ineligible for the bond funds and for federal funds, which are contingent on having state money being available.

In a judgement issued March 4, Judge Michael P. Kenny concurred that the California High Speed Rail Authority does not have sufficient evidence at this time to show that it can comply with all of the requirements of the 2008 bond. The authority, which is charged with building the $64 billion project, has not yet provided the analysis of the trip time from San Jose to the San Francisco Transbay Terminal (its analysis still relies on San Francisco's lone Caltrain station at 4th and King streets, which is about 1.3 miles south of Transbay Terminal), Kenny noted. Nor has it shown that it can achieve a five-minute headway (the amount of time between trains), as mandated by law.

However, Kenny wrote, the rail authority "may be able to accomplish these objectives at some point in the future." He called high-speed rail an "ongoing, dynamic, changing project" and concurred with a recent ruling from the state Court of Appeal, which found that because the project is in flux, it cannot determine whether the project would meet the requirements of the Bond Act.

"There is no evidence currently before the Court that the blended system will not comply with the Bond Act system requirements," Kenny wrote in his ruling. "Although Plaintiffs have raised compelling questions about potential future compliance, the Authority has not yet submitted a funding plan seeking to expend Bond Act funds. Thus, the issue of the project's compliance with the Bond Act is not ripe for review."

Without the necessary analysis, Kenny reasoned, it is premature to determine whether the proposed system would meet the requirements of the 2008 bond. There are, as of today, "still too many unknown variables, and in absence of a funding plan, too many assumption that must be made as to what the Authority's final decisions will be."

By denying the plaintiff's request that the project be halted, Kenny handed a massive victory to what has been a deeply divisive and controversial project. While supporters, including Gov. Jerry Brown and the Democratic majority in the Legislature, consistently laud high-speed rail as a much needed solution to ease traffic congestion, create jobs and reduce greenhouse-gas emissions, critics have panned it as a "boondoggle" that has nowhere near the funds it needs to become a reality.

Palo Alto officials had initially supported the project but ultimately turned against it, passing in 2011 a unanimous resolution calling for the project's termination. At the time, residents and council members raised doubts about the system's financial projections, ridership estimates and proposed alignment, which initially called for four tracks, with an elevated berm in the middle for the new bullet train.

By shifting to the blended approach, which was first proposed by Peninsula lawmakers in 2012, the rail authority has helped qualm some of these anxieties. The project also picked up some momentum last month, when the rail authority released a new business plan showing the price tag dipping from $67.6 billion two years ago to $64.2 billion.

The new business plan also announced a major change of direction for the rail authority: Rather than launching construction of the line exclusively in Central Valley, the agency now plans to build the first operating segment between San Francisco and Bakersfield.

In presenting the business plan to the rail authority's board of director's Tuesday morning, rail authority CEO Jeff Morales called the new proposal "the game-changer, in terms of delivering the program."

The business plan relies mostly on bond funds and on proceeds from the state's cap-and-trade program for building the first operating segment, between the Bay Area and Central Valley. Rail officials hope further improvements and expansions would be financed, at least in part, by private investments and federal contributions.

"For the first time, within available resources, we can actually project out to delivering an operating system," Morales told the board Tuesday.

The board voiced no major concerns Tuesday about the dramatic change of direction in the new business plan. Board member Daniel Curtin said he is "very excited about the new development," which he said would bring new economic opportunities to the two regions that would be connected by high-speed rail.

"We all see the economic pressures being put on the Bay Area by Silicon Valley," Curtin said. "This is a whole change in how that can be approached that, really to me, is the first signal of what high-speed rail will do for California."

Board Chair Dan Richard agreed and lauded the plan for laying out for the public "how we can build the system."

"What is really here, is the sense that we can build this now," Richard said.

Comments

Resident
Old Mountain View
on Mar 9, 2016 at 8:09 am
Resident, Old Mountain View
on Mar 9, 2016 at 8:09 am

This high speed rail project is such a boondoggle. Does anyone here believe anything will ever get built? I'm guessing billions will be squandered on partial tracks before the project goes bankrupt.


Old Steve
Rex Manor
on Mar 9, 2016 at 9:20 am
Old Steve, Rex Manor
on Mar 9, 2016 at 9:20 am

Last week I drove three hours each way for a "can't miss" meeting in Fresno. I had cars waiting I could have used. I had work I could have done on the train. Most Californians will only ride HSR once in a while. Since there will be forty million of us soon, flying does not get easier, and remote conferencing seems to never quite get all the way there, demand for the HSR will likely rise, particularly the next time oil prices surge. Using this money for Water Supply Development would also be illegal.


Martin
Registered user
Rex Manor
on Mar 9, 2016 at 10:42 am
Martin, Rex Manor
Registered user
on Mar 9, 2016 at 10:42 am

Look, most other regions in the developed world with similar populations already have high-speed rail and are quite happy with it. Why shouldn't we in California? I sometimes go to Fresno and Los Angeles and would love to take a train so I could work, instead of my car.


Bill Hitchens
Waverly Park
on Mar 9, 2016 at 4:19 pm
Bill Hitchens, Waverly Park
on Mar 9, 2016 at 4:19 pm

The author is far too optimistic. This is not a "massive victory" by any stretch of the imagination. This merely keeps the project on life support until the HSR has to tap bond money. At that point, this incredibly wasteful and destructive money sink once again will be back in courts; to determine if the HSR Authority can demonstrate that it can present to the courts credible and detailed plans that meet all of the criteria necessary to spend money from the 2008 bonds.

Also, the article conveniently fails to mention that Judge Kenny, as reported on P1 of today's SJ Mercury is quite skeptical of the HSR Authority's ability to comply in the future with the strict terms specifically laid out in the 2008 initiative. "Judge Kenny acknowledged that evidence produced by [the plaintiffs] raises 'substantial concerns' about the rail line's ability to ultimately comply with the bond act. But in the ruling issued Tuesday, which opens the door to future lawsuits, Kenny said the state hadn't crossed the line quite yet."

So, HSR limps on with no new Federal or private sector money in sight.


Gary
Sylvan Park
on Mar 10, 2016 at 6:03 am
Gary, Sylvan Park
on Mar 10, 2016 at 6:03 am

A train just derailed in Alameda County because of a downed tree. Any lone wolf terrorist or radicalized couple could end the use of High Speed Rail (HSR) with a tree branch or other cheap device. $200-$400 billion down the drain. Or how about just an extortionist? One after another. HSR would be such an easy target. BART is already too inviting. Selecting what to build needs to account for realities in the years and decades ahead. Bad guys are not relocating on the moon. They are right here in America and on the way.


USA
Registered user
Old Mountain View
on Mar 10, 2016 at 1:11 pm
USA, Old Mountain View
Registered user
on Mar 10, 2016 at 1:11 pm

He called high-speed rail an "ongoing, dynamic, changing project"

The phrase you are looking for is "out of control".


psr
The Crossings
on Mar 14, 2016 at 12:25 am
psr, The Crossings
on Mar 14, 2016 at 12:25 am

More wasteful spending when there are far more important things that need to be done. Water storage is FAR more important but there are crickets when we ask about new storage. If the cities in the area continue to build without any sign of an actual plan that involves the good of citizens rather than the coffers of the wasteful city and county officials, we will continue to see the quality of life decline.


Name hidden
Blossom Valley

on Mar 16, 2016 at 5:00 pm
Name hidden, Blossom Valley

on Mar 16, 2016 at 5:00 pm

Due to repeated violations of our Terms of Use, comments from this poster are automatically removed. Why?


Don't miss out on the discussion!
Sign up to be notified of new comments on this topic.

Post a comment

On Wednesday, we'll be launching a new website. To prepare and make sure all our content is available on the new platform, commenting on stories and in TownSquare has been disabled. When the new site is online, past comments will be available to be seen and we'll reinstate the ability to comment. We appreciate your patience while we make this transition.